SAP C_TS412_2021 Exam - Free questions
Certification Provider:
SAP
Exam Name:
SAP S/4HANA Project Systems
Exam Code:
C_TS412_2021
C_TS412_2021 Free Questions:
Below you can find SAP S/4HANA Project Systems exam free sample questions which will help you to prepare for your upcoming SAP certification exam. These questions will give you an idea of what to expect on the exam and help you review the C_TS412_2021 study material provided in SAP Learning hub. However we recommend that you enrol in premium SAP C_TS412_2021 questions which will guarantee you to pass your exam.
These C_TS412_2021 questions are updated frequently, so you can be confident that you're studying with the most up-to-date information available. ExamStudyZone also provides answer keys so that students can check whether their answers are correct or not.
Additionally, going through SAP S/4HANA Project Systems practice questions can help you identify any areas where you need more review. Taking advantage of our C_TS412_2021 demo questions is a great way to set yourself up for success on the real exam.
Question No. 1) What could be a reason to use expert mode in the valuation method for results analysis?
Options:
A) Billing WBS elements belonging to different company codes
B) Assignments of different accounts for postings to financial accounting
C) Usage of different line ID
D) Valuation in different currencies
Question No. 2) What are some of the possible functions in user status profiles? (2 correct)
Options:
A) Ensure user status must always be set manually
B) Allow business processes forbidden by SAP system status
C) Restrict setting user status for individual users
D) Utilize priorities for setting the user status
Question No. 3) Which of the following business processes do NOT lead to the booking of actual costs to an object? (2 correct)
Options:
A) Goods receipt into unvaluated project stock
B) Recording of external services in the service entry sheet
C) Goods receipt of a non-stock item
D) Goods receipt into valuated project stock
Question No. 4) Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget updates. What standard report do you recommend?
Options:
A) Structure overviews for budget.
B) Cost element report on budget updates.
C) Line item report for budget
D) Hierarchical report on budget updates.
Question No. 5) Which object is used to allocate the costs from a claim to the project structure?
Options:
A) Network activity
B) Internal order
C) Claim
D) WBS element
Question No. 6) Your customer want to use scheduling for network to specify planned dates of task. In the SAP project system there are different set of dates that can be scheduled. Which set of dates can be used for scheduled for network? (2 correct)
Options:
A) Planned dates
B) Fundamental dates
C) Basic dates
D) Baseline dates
E) Forecast dates
Question No. 7) You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling. What do you check? (2 correct)
Options:
A) If the maximum reduction level is less than 100
B) If the reduction strategy is set in the network header
C) If the reduction strategy is set in each activity
D) If the appropriate reduction type is set in the parameters for network scheduling
Question No. 8) You Want assign milestone to WBS element? For what can you use these milestone.
Options:
A) To create standard network
B) To start workflow task.
C) For trend analysis.
D) To set an actual finish date for WBS element-Question
Question No. 9) How can you record external service activities with service master data? (2 correct)
Options:
A) Confirm the network activity for external service
B) Confirm the activities in the Cross-Application Time Sheet (CATS)
C) Post a goods receipt in the goods movement application (MIGO)
D) Create a service entry sheet
Question No. 10) Which statement regarding the creation of a new work breakdown structure (WBS element) are true? (3 correct)
Options:
A) You can create several WBS elements per level.
B) A new work breakdown structure must contain up to 10 levels.
C) A WBS element of the new project can be assigned to a different project definition.
D) WBS element can be a planning element, an account assignment element, and a billing element at the same time.
E) The WBS structure can contain several level 1 WBS element, (es configurable por perfil de proyecto)
Many students have gone through these questions along with premium tests and cleared their exam.
C_TS412_2021 Exam Answers